Topsoil Calculator

Cubic yards of topsoil = length × width × depth (in) ÷ 324, plus extra for settling. A 30 × 20 ft lawn at 6 in settled is 11.11 yd³; with 25 % for settling, order 13.89 yd³. For a new lawn, Virginia Cooperative Extension asks for 8 to 10 in of loose topsoil, which settles to 6 to 8 in.

Units

Virginia Cooperative Extension: 10 in of loose topsoil settles to about 8 in (+25 %). Enter 0 for a raised bed you top up later.

Pacific Topsoils: 2,000 lb per cubic yard dry (1 ton), 2,200 lb wet (1.1 tons).

Topsoil to order

13.89 yd³

13.89 tons · 375 ft³

Spread it loose at
7.5 in
Volume after settling
11.11 yd³
Weight
13.89 short tons · 12.6 t
1 cu ft bags
375
0.75 cu ft bags
500
Area
600 ft²

Worked examples

A 30 × 20 ft new lawn, 6 in deep after settling

  1. 30 × 20 = 600 ft²; 600 × 6 ÷ 12 = 300 ft³ = 11.11 yd³ once settled
  2. 300 × 1.25 = 375 ft³ = 13.89 yd³ to order, spread 7.5 in loose
  3. 13.89 yd³ × 1 ton = 13.89 tons of dry topsoil

Result: Order 13.89 yd³, about 13.89 tons dry.

Checked by the automated test “topsoil — 30 × 20 ft lawn at 6 in settled = 11.11 yd³; order 13.89 yd³ = 13.89 tons dry”.

An 8 × 4 ft raised bed, 12 in deep, filled with bags

  1. 8 × 4 × 12 ÷ 12 = 32 ft³ = 1.19 yd³ (settling set to 0 %)
  2. 32 ÷ 1 = 32 bags of 1 cu ft, or 32 ÷ 0.75 = 42.7 → 43 bags of 0.75 cu ft

Result: 1.19 yd³: 32 bags of 1 cu ft or 43 bags of 0.75 cu ft.

Checked by the automated test “topsoil — 8 × 4 ft bed at 12 in, 0 % = 32 ft³ = 1.19 yd³ = 32 bags of 1 cu ft”.

How it works

Settled volume (ft³) = length (ft) × width (ft) × depth (in) ÷ 12

Volume to order = settled volume × (1 + settling % ÷ 100)

Cubic yards = ft³ ÷ 27 · Tons = cubic yards × soil weight (tons per yd³)

Assumptions

  • Default settling allowance 25 %: Virginia Cooperative Extension calls for 8 to 10 in of loose topsoil to end up with 6 to 8 in after settling (10 ÷ 8 = 1.25).
  • Default soil weight 1 ton per cubic yard (2,000 lb), the dry weight Pacific Topsoils lists for its 3-way topsoil; it lists 2,200 lb for the same soil wet. Use your supplier's figure.
  • Tons are US short tons (2,000 lb). Bags are counted on the volume to order and rounded up.

Reference table

What one cubic yard covers, and what 1,000 ft² needs with 25 % for settling
Settled depth1 yd³ covers1,000 ft² needsWeight, dry–wet
1 in324 ft²3.86 yd³3.9–4.2 tons
2 in162 ft²7.72 yd³7.7–8.5 tons
3 in108 ft²11.57 yd³11.6–12.7 tons
4 in81 ft²15.43 yd³15.4–17 tons
6 in54 ft²23.15 yd³23.1–25.5 tons
8 in41 ft²30.86 yd³30.9–34 tons
12 in27 ft²46.3 yd³46.3–50.9 tons

Weights at 2,000 lb (dry) and 2,200 lb (wet) per cubic yard, Pacific Topsoils' 3-way topsoil.

Topsoil, fill dirt or garden mix

Common mistakes

Frequently asked questions

How much does a yard of topsoil weigh?

About 2,000 lb (1 ton) dry and 2,200 lb wet, the figures Pacific Topsoils gives for its 3-way topsoil. Blends with compost weigh less: use the weight on your quote.

How many cubic feet are in a yard of dirt?

27 cubic feet: a cubic yard is 3 ft × 3 ft × 3 ft (NIST Handbook 44). One cubic foot is 0.037 yd³.

How much will a yard of soil cover?

324 ft² divided by the depth in inches: 81 ft² at 4 in, 54 ft² at 6 in. That is the settled depth, so add the settling allowance to your order.

How much topsoil will I need?

Multiply the area by the depth you want after settling, divide by 324 for cubic yards, then add 25 %. For 1,000 ft² at 4 in: 12.35 yd³ settled, 15.43 yd³ to order.

How many bags of topsoil are in a yard?

A cubic yard is 27 ft³, so 27 bags of 1 cu ft or 36 bags of 0.75 cu ft. The result gives both bag counts for your own area and depth.

Sources

Formula, examples and sources checked on by the Yardstick Math team. How we check our formulas.

  1. Safe hauling of bulk materials – cubic yard weights (3-way topsoil 2,000 lb dry, 2,200 lb wet) — Pacific Topsoils, accessed
  2. Gardener Handbook, Chapter 11: Lawns (8 to 10 in loose for 6 to 8 in settled) — Virginia Cooperative Extension, accessed
  3. Handbook 44, Appendix C – General Tables of Units of Measurement (1 yd³ = 27 ft³) — NIST, accessed